The Edward R. Roybal Learning Center took a long and difficult path to completion. Construction at the school site began in the late 1990s but was shut down two separate times after seismic and environmental conditions were discovered. The project site sat dormant for three years, but in 2005, the Los Angeles Unified School District awarded new contracts to an architect and general contractor who were tasked to take the project and turn it into the desperately-needed school for the city.
When completed in September 2008, the renamed Edward R. Roybal Learning Center is a 34 acre, 610,000 sq. ft., 2,800-seat year-round high school, consisting of seven small learning communities. One of the challenges of building the school was incorporating already-constructed buildings with new construction plans.
The project team took four of the partially-constructed buildings from the unfinished school and created 88 classrooms. New construction included a 55,000-sq-ft auditorium, library, cafeteria building, and a 55,000-sq-ft classroom/administration building, all contained within a 50-foot earthquake fault setback for seismic safety. The campus also features a large gymnasium with locker rooms and outdoor athletic facilities as well as a central utility plant. The project team also installed an elaborate methane barrier accompanied with a methane exhaust system underneath portions of the project to provide a double barrier of protection from methane gases – one of the environmental issues that had stopped construction.
The methane mitigation system traps gases through sand, soil, and a plastic membrane and when levels are high, vents them through conduits located in and around the school. All buildings were set back the minimum fifty feet from the earthquake fault, which meant demolishing one of the four already-built classroom buildings and administration building and replacing it with another classroom building and a multipurpose building that includes a cafeteria, a library, a bookstore, music and dance rooms, and maintenance offices.
This LAUSD project is the recipient of several awards, including the prestigious 2009 Marvin M. Black Excellence in Partnering Award.